Boulevard Contractors settlement — 32 North Potomac Street

Hagerstown

Summary

The renovation of the former M&T Bank building ran over a year late with quality problems, and the city is holding $243,000 in retainage. The proposed settlement gets subcontractors paid while the city forgoes liquidated damages rather than risk arbitration.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 22, 2026.

Impact analysis

💰Financial impact

The city gives up potential liquidated damages worth a share of $243,000 but avoids further legal fees and arbitration risk.

✅Who benefits

Subcontractors owed money on the project get paid in full.

⚠️Who could be affected

Taxpayers absorb the loss of damages the city might have recovered in arbitration.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Hagerstown

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.